Background

 

 

 

In 1991 Welsh Water introduced annualised hours, or ‘planned working time’ (PWT), on a trial

basis, for about 100 employees in the Gower area of its south-west division.

 

Traditionally overtime working has been high in the industry and represented a significant cost to the organisation.

 

Weekend working and emergency work (for example, repairing burst water mains) was covered on an overtime basis, and because of the dispersed nature of the organisation overtime was difficult to control.

 

After a reduction in working hours at national level from 39 to 38 in 1982, manual employees had been finishing early at 2:00 pm on Fridays since 1982.

 

‘Staff employees’ were already on 37 hours and the company wanted to end this early finish and harmonise hours for all employees.

 

 

The annualised scheme was extended to other areas of Welsh Water from 1992-3 onwards.

 

 

 

 

 

 

Case Study: Welsh Water - Annualised Hours 

 

Annualised Hours Scheme has benefited company and employees.

 

These changes were achieved through the implementation if a ‘Partnership Agreement’ in April 1991, which aimed to establish single-status conditions for all staff and covered wide-ranging revisions to pay and working conditions.

 

The agreement offered area managers one of two different working arrangements, which were to operate on a 12-month trial basis. The first was planned working time (PWT); the second was a ‘lieu time’ arrangement, with one day being rostered off every four weeks.

 

The aim of the PWT scheme is to provide a mechanism, which ‘facilitates the introduction of different pre-planned patterns of work more closely related to the needs of the business’. There is a basic contract of 1,664 hours per year (which is equivalent to the 37-hour week after allowing for holidays) and where there is a need to cover work outside basic hours, additional hours, known as ‘hours plus’ are added to form the ‘total contract hours’.

 

These hours vary between 218 and 332 according to section and have two elements; ‘committed hours’ i.e. hours needed to deliver an agreed pattern of work, and ‘uncommitted hours’ which are unrostered and used for emergency work, sickness, absence, etc. These hours have been set at a level that assumes that only 75-80% will be used under normal circumstances, the surplus allowing for major emergency.

 

Benefits for the Company

 

The trial scheme has shown considerable benefits. Financially there have been positive savings in all areas where PWT was introduced, in comparison with the lieu time arrangements, where there have been no cost savings.

 

These savings range from 14.1% to 5% over the 5 per cent needed to ‘break even’ as a result of the cost of reduced working hours.

 

Other benefits have been:

  • Increased job output;

  • Vehicle and plant maintenance carried out outside the normal working day allowing reductions in vehicle fleet;

  • Positive business attitude among employees and better co-operation;

  • More flexible and committed workforce;

  • Improved management control;

  • Reduced absenteeism attributed to peer group pressure as a result of PWT.

 

 

Benefits for the Employee

 

Employees have also seen the benefits of the scheme in the form of higher guaranteed salary, which is reflected in holiday and pensionable pay, more time off, which can be arranged in bigger ‘chunks’, and the ability to plan ahead in terms of income and time off.

 

On the downside, holidays are rostered (although there is some flexibility built in to take time off), the potential for overtime earnings is capped and employees are obliged to work up to a certain level of ‘contractual overtime’.

 

Despite these drawbacks, many employees in other areas of Welsh Water are now asking to be on the planned working time, and the company is keen that all areas look at its potential implementation.

 

 

* Extracted from an article on Annual Hours by Sue Hutchinson Personnel Management April 1993.

 

The consultancy work referred to in this case study was carried out by Philip Lynch Associates in 1991. 

 

 

For further details of our services, or to arrange a face-to-face or telephone discussion, please contact us.

 

Contact Information

EMail:  info@workforce-logistics.com

Phone:   +44 (0)1709 - 326518